ER '97 Workshop 7 Pollution Prevention and Waste Minimization Principles
INTRODUCTION
Objectives
To raise awareness and provide guidance in integrating
pollution prevention (P2) into environmental restoration activities,
to present case studies that demonstrate the viability of incorporating
these P2 principles, and to discuss the benefits and results of
applying P2 techniques in reducing waste volumes and overall project
costs.
In addition, the workshop was designed to raise the
awareness of and convince the workshop participants that incorporation
of P2 and waste minimization principles into environmental restoration
projects can be done successfully and results in added value (i.e.,
reduced waste volumes and lower waste management costs) which
will contribute to achieving the goals of the Ten-Year Plan.
The workshop made clear that early integration of
P2 and waste minimization concepts in project planning results
in both successful reduction of waste volumes and lower waste
management costs, and would be integral to the success of the
Ten-Year Plan.
At the request of a full house of interested participants,
the workshop was extended an additional hour, allowing eight presentations
and meaningful interaction between the panelists and the audience.
Workshop Organizers/Facilitators
|
Bob Fleming (Facilitator) DOE Office of Environmental Restoration
19901 Germantown Road
Germantown, MD 20874-1290
Phone 301-903-7627
robert.fleming@em.doe.gov |
Lisa Allmon-Burns (Facilitator)
IT Corporation
11499 Chester Road
Cincinnati, OH 45246-4012
Phone 513-782-4684
lallmon@primax.net |
Panel Members
Jason Darby
Applied Technologies FUSRAP
P.O. Box 2001
Oak Ridge, TN 37831-8723
Phone: 423-241-6343
darbyjd@oro.doe.gov |
Steve Hauser
Fluor Daniel Fernald
P. O. Box 398704
Cincinnati, OH 45239
Phone: 513-648-4126
steve.hauser@fernald.gov
|
Paul Hauber
Becthel Savannah River
Building 730-2B, Room 319
Aiken, SC 29802
Phone: 803-952-8718
paul.huber@srs.gov |
Paul Larson
LMES-OR
P.O. Box 2003
Oak Ridge, TN 37831-7046
Phone: 423-574-9905
el2@ornl.gov |
Bill McConachie
Lawrence Livermore National Laboratory
7000 East Avenue, MS L544
Livermore, CA 94550
Phone: 510-423-3501
mcconachie@llnl.gov |
Gerry Maul
EG&G Mound
P.O. Box 3000
Miamisburg, OH 45343-3000
maulgf@doe-md.gov |
Roy Michelotti
Los Alamos National Laboratory
P.O. Box 1663, MS M992
Los Alamos, NM 87545
Phone: 505-665-7444
roym@lanl.gov
| Ana Rosado-Gonzalez
DOE Oak Ridge Operations Office
P.O. Box 2001
Oak Ridge, TN 37831
Phone: 423-241-4242
gonzalezal@oro.doe.gov
|
Tom Wilczek
IT Corp., Las Vegas
4330 S. Valley View
Las Vegas, NV 89103
Phone: 702-794-1700
twilczek_it@nv.doe.gov
|
|
PRESENTATION SUMMARIES
This section contains a brief summary of each panelist's
presentation. Full presentation graphics or papers may be obtained
by contacting the panelists.
P2 Concepts Used During the Oak Ridge K-25 Site Cooling Towers
Demolition
Paul Larson
LMGS-OR
Paul Larson discussed the large-scale demolition
project known as the K-25 Site Cooling Towers Demolition and focused
on the development of a free-release protocol, which enabled the
project team to characterize and release facilities and materials
for recycle and reuse. The proactive, early P2 planning by the
team resulted in cost savings of $3.5M (out of a $22M baseline
estimate).
The Fernald Integrated Approach to P2 Utilization
During Decontamination and Dismantlement Projects
Steve Hauser
Fluor Daniel Fernald
Steve Hauser presented a brief overview of the Fernald
Environmental Management Project (FEMP) decontamination and dismantlement
(D&D) planning process and how early considerations of P2
and waste minimization concepts and principles were incorporated
up front to facilitate building debris disposition. Recycle and
reuse examples, future opportunities for recycle of carbon steel,
and issues surrounding the decision making processes for recycling
versus other disposition options were also covered.
Nevada Test Site Application of P2 During Characterization
Activities
Tom Wilczek
IT Corporation
Tom Wilczek discussed an underground storage tank
remedial action at the Nevada Test Site (NTS). The project team
formed a P2 working group and developed and implemented an inexpensive,
innovative, and highly effective sampling tool to address sampling
problems encountered during characterization activities. This
sampling tool reduced the characterization costs by $17,000 and
resulted in a large volume reduction of decontamination rinse
waste and avoided excessive waste management costs.
Cost Savings Success via Lawrence Livermore National
Laboratory's Cost-Effective Sampling Technique
Bill McConachie
Lawrence Livermore National Laboratory
Bill McConachie discussed Lawrence Livermore National
Laboratory's (LLNL's) development and use of the Cost-Effective
Sampling technique, which enables the sampling of ground water
wells in a logical, clearly-defined manner so that sampling frequencies
can be reduced (or modified) for wells that do not show a change
in contaminant concentration over time. He provided strategies
for dealing with the regulators on these types of issues. Results
of applying this methodology at LLNL included 594 fewer samples
collected, a 20,000-gal reduction in waste water volume, and FY
1996 cost savings of approximately $400,000.
Segregation Technology Reduces Waste Volumes
for Formerly Utilized Sites Remedial Action
Program
Jason Darby
Utilized Sites Remedial Action Program (Formerly)
Jason Darby discussed the application of the Segmented
Gate System (SGS) technology at several Formerly Utilized Sites
Remedial Action Program (FUSRAP) sites and explained the up-front
evaluations performed to determine the cost effectiveness of implementing
the technology. SGS separates (segregates) materials containing
radioactive contamination from large volumes of excavated soil,
resulting in large reductions in waste disposal volumes and waste
management costs. For example, the New Brunswick Site achieved
a 55% reduction in disposal volume and an estimated $1.2M cost
savings.
Uranium Soil Cleanup - A Pilot Project Using the
Segmented Gate System in Conjunction with
Containerized Vat Leaching
Roy Michelotti
Los Alamos National Laboratory
Roy Michelotti discussed the combination of the SGS
industrial process with the Los Alamos National Laboratory (LANL)
Containerized Vat Leaching (CVL) technology to conduct a clean-up
pilot project with the objective of generating cost and applications
data to evaluate appropriateness at other larger sites. Significant
cost savings over the conventional dig-and-haul approach resulted.
Beneficial Reuse of Metal from Special Metallurgical
Building Demolition at the Mound Plant
Results in Project Cost Savings
Gerry Maul
EG&G Mound Applied Technologies
Gerry Maul discussed the D&D of the Special Metallurgical
Building and the integration of P2 techniques early in the planning
phase of the project. He included how the project team evaluated
the cost effectiveness of smelting the metal from the building
demolition for beneficial reuse and how the team calculated the
final cost avoidance. Smelting of 300,000 lb of steel for use
as shield blocks at the LANL and the disposal at the NTS of only
37,000 lb of returned material resulted in project cost savings
of $155,000 over baseline estimates.
Radiologically Contaminated Equipment Decontamination,
Recycle, and Reuse at the Savannah River Site
Paul Huber
Bechtel Savannah River
Paul Huber discussed the use of a decontamination
and recycle/reuse subcontract to clean heavy construction equipment
that was contaminated during the closure of the M- Area Settling
Basin. The cleaning of the equipment enabled the material to
be either recycled or reused instead of disposed as low-level
waste (LLW) or mixed waste. The best value approach generated
project cost savings of more than $1M.
DISCUSSION SUMMARY
Extensive interaction occurred between the presentation
panelists and the audience participants during this workshop,
requiring an hour-long extension of the workshop. The combination
of the successful application of P2 and waste minimization techniques
presented by the panelists and the questions, answers, and exchange
of information discussed with participants is captured as responses
to the ten questions of the ER '97 workshops.
1. What activity, position, approach, method
of performance, etc., was successful and why?
The proactive, early P2 and waste minimization
planning by the Environmental Restoration project teams resulted
in significant volume reductions and cost savings. The following
are examples.
- Development of a Release Protocol
To maximize the commercial recycle or disposal
of materials from the demolition process, a protocol for release
of facilities for recycle/disposal was developed for the K- 25
Site Cooling Towers Demolition Project. With the U.S. Department
of Energy (DOE) and the State of Tennessee concurring on the protocol,
the project team was able to decontaminate and subsequently determine
that any radioactive contamination was below the regulatory requirements
for these facilities, thus making them candidates for commercial
recycling/disposal. This proactive planning resulted in free
release of approximately 1,700,000 lb of nonradioactive scrap
metal for recycling, netting approximately $2.5M in cost savings.
The concrete rubble generated during demolition was used on site
as fill material as part of a State-approved, unpermitted landfill,
avoiding additional project costs for transporting and disposing
of the concrete rubble. Without the up-front development, negotiation,
and acceptance of the "free release" protocol, the cost
associated with the traditional approach would have required the
disposal of 5,500 yd3 of concrete rubble. With an estimated disposal
cost for LLW of $27/yd3, the project's approach resulted in a
cost avoidance of $148K. Also addressed was the handling of approximately
900,000 gal of free-standing water that had accumulated in the
basins. The project team negotiated with the State to allow the
use of this water for irrigation of grassy fields, thus saving
approximately $870K. As a result of incorporating P2 and waste
minimization early in the project planning, a total cost savings
of approximately $3.5M was realized.
- Improved Waste Management
A detailed decision process for dispositioning
debris resulting from D&D of Fernald buildings is part of
the planning phase of each project. Secondary waste generation,
including wash-down water and personal protective clothing, is
estimated, and opportunities are evaluated to minimize the generation
of these wastes. Structural steel and lead sheet metal have been
decontaminated for free release. The conclusion is that the successful
project cost reduction coincides with improved waste management.
- Decontamination and Recycling
Large contaminated equipment used during the
closure of the M-Area Settling Basin at the SRS needed to be dismantled
and disposed of because of the radiological hazard it posed.
Decontamination and recycling/reuse resulted in significant cost
savings and volume reductions. When compared with the dismantling
and disposal option, decontamination and recycling/reuse saved
more than $1M and reduced the projected waste volumes from 13,500
to 6 ft3 for LLW and from 1,200 to less than 50 ft3 for mixed
LLW.
- Smelting of Metal versus Disposal
The cost of the conventional disposal approach
for contaminated metal from D&D of the Special Metallurgical
Building at the Mound Plant was estimated at $500K. Mound also
evaluated and estimated the cost of smelting the metal and sending
the secondary waste slag to the NTS. This cost was estimated at
approximately $268K. The smelting option was selected. Approximately
300,000 lb of steel was smelted, 21,000 lb of aluminum scrap was
compacted, and 16,000 lb of slag was generated. Total cost of
this option was $395K for a total savings of $105K off the baseline
estimate. Although the P2 and waste minimization alternative encountered
a number of hurdles, the conclusion is that it was the cost-effective
and environmentally correct way to go.
2. What activity, position, approach, method
of performance, etc., was unsuccessful and why?
New Waste Stream Through Cross-Contamination
During the discussion of the successful smelting
experience at the Mound Plant, a member of the audience shared
his melting experience on a FUSRAP project. In this case, overall
project costs were increased because of the need to dispose of
a new waste stream that was created from cross-contamination,
thus making the beneficial reuse option less attractive.
3. What new P2 and waste minimization concept(s)
have been identified and applied, and what were the results?
- P2 Information Management System
The new P2 Information Management System developed
and managed out of the Oak Ridge Operations Office tracks and
documents P2 opportunities that result in cost savings from the
avoidance or reduction of generated waste. P2 Opportunity Assessments
are performed on waste-generating activities such as decommissioning
or remediation to determine the most efficient use of resources.
The system can be used to prepare performance measures, project
update sheets, and required reports. The system has been tailored
to ER projects and assists project managers in documenting successful
P2 methods/techniques employed during the project.
- Incentive Task Order Contracting
The K-25 Site Cooling Towers Demolition Project
work was performed using an Incentive Task Order Contract. Performance
specifications allowed the contractors to be innovative. End results
and project criteria rather than methods of accomplishment were
specified. The project team issued clear and concise, integrated,
project-specific procurement packages bound as one document. The
integrated procurement package resulted in the average bids being
within 1% of the DOE estimate. The three awarded bids were, on
average, 28% lower than the DOE estimate. The estimated cost
at completion of the project was $19M, resulting in a total savings
to DOE of approximately $4M. The project was also completed three
months ahead of schedule.
- "Best Value" Contract for Decontamination Vendor
Savannah River embarked on an effort to obtain
the services of a commercial vendor to decontaminate and recycle/reuse
the large equipment used for the M-Area Settling Basin closure.
A competitive "best value" contract was awarded. The
contract also included incentives that required the selected vendor
to minimize to the maximum extent possible the volume of secondary
wastes generated. This approach not only resulted in cost savings
of more than $1M but also reduced the projected waste volumes
from 13,500 to 6 ft3 of LLW and from 1,200 to less than 50 ft3
of mixed LLW.
4. What new P2 and waste minimization technologies
have been identified and applied, and what were the results?
- Alternate Sampling Technologies
During site characterization activities, NTS
project personnel discovered approximately 40,000 gal of uncharacterized
multiphasic substances in four 10,000 gal underground storage
tanks. Drilling muds that had settled at the tank bottoms broke
the composite liquid waste samplers, necessitating use of alternate
sampling technologies. Acrylic samplers cost $1,200 each and would
require decontamination after each use, increasing the volume
of secondary waste. Project personnel consulted with a national
laboratory metallurgist, who recommended commercial-grade copper
pipe. For a total of $2,400, the team purchased copper pipe from
a local supplier, cut it into 10-ft lengths, and equipped each
section with check valves. They then installed one copper pipe
device in each sampling location. Uncontaminated samplers were
removed and reused. Contaminated samplers were left in the tanks
until characterization was completed. Use of this sampling tool
for this phase of the project reduced project costs by $17,000
and minimized waste stream generation. The technology is easily
modified for application at other restoration sites.
- Cost-Effective Sampling
Sampling to evaluate contaminant migration and
the effectiveness of cleanup generates large volumes of waste
water that must be collected, transported, and treated before
discharge. Additionally, it is difficult and time consuming to
evaluate the data manually because of the large number of wells
sampled and the amount of data collected. LLNL developed a Cost-Effective
Sampling (CES) methodology and associated software for estimating
the lowest monitoring well sampling frequency required to provide
adequate data for remedial action and compliance-related decisionmaking.
It resulted in a reduction of 35,868 gal of waste during the collection
of ground water samples by reducing the amount of samples taken
during the remedial investigation. The CES process saved approximately
$400,000 in FY 1996 and has regulator and stakeholder concurrence.
- Separation of Radioactive Soils
During cleanup of a FUSRAP site in New Brunswick,
NJ, approximately $1.2M was saved by applying the SGS to the contaminated
soil cleanup. Designed and operated by Thermo Nuclean, this technology
effectively separates materials containing radioactive contamination
from large volumes of excavated soil. This application resulted
in a 55% reduction in the amount of waste disposed offsite. At
another FUSRAP site, the Middlesex Sampling Plant, of the 200
yd3 processed for the test, more than 90% met clean-up criteria.
Use of this technology at Middlesex for large-scale cleanup could
reduce remediation costs by 50% or more.
- Separation and Leaching Technologies
LANL combined the SGS process with CVL to conduct
a clean-up pilot project. After 220 yd3 of contaminated soil was
processed through the SGS and CVL, 211 yd3 was returned to the
site as clean. Combining these technologies has the potential
to save $46M to $52M for DOE if used for the remediation of the
100,000 yd3 swatches of contaminated soil at LANL. Larger sites,
such as Mound and Fernald, are also looking at large-scale use
of these technologies.
5. For the subjects of P2 and waste minimization
discussed, what issues were identified and how were they dealt
with? What issues remain to be resolved and what approaches were
proposed?
- Internal Issues
During the evaluation period for deciding between
the conventional disposal approach for contaminated metal from
the D&D of the Special Metallurgical Building at the Mound
Plant and the smelting alternative, a number of issues/hurdles
arose. Lawyers were concerned about the liability for the release
of non-real Government property. This concern was resolved with
the approach that all metal product would be shipped to LANL for
use as shield blocks, and slag from the smelter would be returned
to Mound for disposal. The purchasing agent wanted the work to
be bid competitively, but no other bidders existed. Waste Management
personnel were concerned initially because of the different waste
form. This concern was resolved after a waste management audit
was conducted at the smelting site.
- External Regulator Issues
Regulator acceptance and/or approval was necessary
for use of the copper pipe sampling device at the NTS, the LLNL
methodology to reduce sampling frequency, and the free-release
protocol at the K-25 Site Cooling Towers Demolition Project. In
each case, project personnel involved regulators in thinking through
and planning the P2 and waste minimization opportunities, typically
engaging them early in the project. Regulator concurrence resulted
in each case.
6. For the subjects of P2 and waste minimization,
what decisions were made? What decisions remain to be made and
what was recommended?
Early Integration of P2 and Waste Minimization
in Project Planning P2 and waste minimization should be factored
into the environmental restoration and D&D processes early
on in the planning phase. P2 and waste minimization practices
should be encouraged and required because of the measurable degree
of success. Furthermore, the integration of P2 Opportunity Assessments
into the environmental restoration and decommissioning processes
is highly recommended because waste stream volumes would be minimized;
results of P2 implementation would be measured properly, quantified,
and documented for use on other projects; and negative impacts
to human health and the environment would be decreased.
7. For the subjects of P2 and waste minimization,
what data are important and play a crucial role in the outcome?
What data remain to be collected, and how is collection recommended?
- Socioeconomic Evaluation
If one refers to the Fernald decommissioning
experience, materials potentially suited to recycling should be
subjected to a detailed socioeconomic evaluation to document which
disposition alternatives present the best balance of stakeholder
preference, risk, and life-cycle cost. Stakeholder/regulator
input continues to favor recycle/reuse options; however, site
economics may prescribe disposal, particularly where on-site disposal
cells are available.
- Documentation/Tracking and Lessons Learned/Transfer
of Info
Understanding of the results and benefits of
P2 and waste minimization principles should move beyond "anecdotal
awareness," as a member of the audience characterized it,
to demonstrable links between specific P2 and waste minimization
activities and cost savings, risk reduction, environmental protection,
and other positive outcomes. Data supporting these links should
be collected and disseminated. Development of computer software,
such as the tracking system under development at Oak Ridge, is
part of the answer. Information exchange opportunities, such as
this workshop, and publication of project results also contribute
to the demonstration of beneficial results associated with P2
and waste minimization.
8. For the subjects of P2 and waste minimization
discussed, what next steps were identified and responsibilities
assigned or advocated?
Because of the range of understanding for incorporation
of P2 and waste minimization principles in environmental restoration
and decommissioning activities, the workshop organizers assumed
the responsibility of reviewing what has actually been formalized
within the DOE Environmental Restoration system and evaluating
the need to update and strengthen that which is already in place
and disseminate it to the field. This activity will include looking
at P2 and waste minimization tools for training, tracking, and
information exchange that different sites either have in place
or are developing to identify any with Environmental Restoration
Program-wide application.
9. For the subjects of P2 and waste minimization
discussed, what agreements or disagreements were voiced? Was consensus
reached on one or more positions (or opinions) for actions or
approaches not yet taken?
- Factor in P2 and Waste Minimization Early
Workshop participants agreed fully that P2 and
waste minimization principles should be factored into and evaluated
in the environmental restoration and decommissioning projects
early on to reap the largest cost savings to the Environmental
Management complex.
- Incentivize Contracts
P2 and waste minimization incentives should be
incorporated in environmental restoration and decommissioning
project contracts to require contractors to plan consciously to
reduce volumes of primary and secondary wastes destined for disposal.
- Share Lessons Learned and Transfer Information
Clean-up site workshops need to take place on
a timely, regular basis to share successes and lessons learned,
such as those discussed in this workshop. (See also responses
to Questions 1 through 4.) Holding the ER '97 workshops in conjunction
with the WM '97 Conference was a cost-effective method to accomplish
this need. Subsequent site specific visits and relevant briefings
on new P2 tools will also be necessary for in-depth discussions
and viewing of the techniques at work.
- Document and Track
Workshop participants agreed that a system should
be developed and implemented to facilitate the actual tracking
and documentation of P2 and waste minimization processes. Site
project personnel found it difficult at best to perform necessary
tracking and documentation.
10. What Departmental or other policies/procedures
were explained in the workshop?
Policies Used
The K-25 Site Cooling Towers Demolition Project team
used DOE Order 5400.5, NUREG 1.86, and NUREG 5849 as bases for
the development of the protocol for radiological release of facilities
for recycle/disposal. This step was taken to maximize the commercial
recycle or disposal of materials from the demolition process.
The project was able to recycle scrap metal commercially, reuse
concrete rubble, and cost effectively handle large volumes of
basin water, resulting in a total cost savings of approximately
$3.5M.
CONCLUSION
P2 and waste minimization principles have been applied
to environmental restoration and decommissioning projects and
have been both successful in reducing large volumes of wastes
destined for disposal and effective in reducing waste management
costs. P2 and waste minimization should be incorporated early
in the project planning process by thoroughly integrating the
concepts into the project teams and evaluating forecasted waste
streams for P2 and waste minimization opportunities. Documentation
and dissemination of successful (and not so successful) methods
and techniques to other sites performing cleanup are also necessary
to demonstrate the links between P2 and waste minimization activities
and their results. With the inclusion of P2 and waste minimization
concepts into environmental restoration and decommissioning projects,
DOE can reduce significantly the amount of primary and secondary
wastes that require treatment and disposal. This action would,
in turn, reduce risks to the workers, the public, and the environment,
and lower overall project and DOE waste management costs, ultimately
contributing to the success of the Ten-Year Plan.
REFERENCES
Complex Wide Study on the Successful Integration
of Pollution Prevention into the Environmental Restoration Program,
U.S. DOE, Office of Environmental Restoration, Executive Summary
and Vols I and II, IT Corporation, September 31, 1996.
Pollution Prevention and Waste Minimization Guidance
for Environmental Restoration Activities, U.S. DOE, Office of
Environmental Restoration, May 1995.
Brochure on the Pollution Prevention Information
Management System, U.S. DOE, Office of Pollution Prevention, Lockheed
Martin Energy Systems, 1997.
Video, Tooling Up for Success Integrating P2 into
ER, U.S. DOE, Office of Environmental Restoration, Bechtel Nevada
Remote Sensing Laboratory Video Services, 1996.
Send all comments, technical questions, and requests for password access to:
HSS User Support
P2Support@hq.doe.gov
(800) 473-4375
|