The 2011 Facility Representative/Safety System Oversight Workshop
May 2 - 6, 2011 Las Vegas, NV |
| Workshop Agenda and Presentations |
Monday and Tuesday, May 2-3, 2011 Training Courses |
| 8:00 a.m. to 5:00 p.m |
Configuration Management Integration of Safety into the Design Process |
Wednesday, May 4, 2011 Plenary Session |
| 8:00 a.m. |
Welcome to the 2011 Facility Representative/Safety System Oversight Workshop
Earl Hughes, Facility Representative and Safety System Oversight Program Manager
Office of Nuclear Safety Policy and Assistance
Office of Health, Safety and Security |
|
| 8:05 a.m. |
Welcome from the Nevada Site Office
John Mallin, Deputy Assistant Manager for Site Operations
Nevada Site Office |
|
| 8:30 a.m. |
Opening Remarks
Glenn Podonsky, Chief Health, Safety and Security Officer Office of Health, Safety and Security |
|
| 8:45 a.m. |
Facility Representative and Safety System Oversight Award Ceremony
Glenn Podonsky, Chief Health, Safety and Security Officer
Office of Health, Safety and Security
Earl Hughes, Facility Representative and Safety System Oversight Program Manager
Office of Nuclear Facility Safety Programs
Office of Health, Safety and Security |
|
| 9:30 a.m. |
Break |
| 10:00 a.m. |
Perspective from the Defense Nuclear Facilities Safety Board
The Honorable Joe Bader
Member, Defense Nuclear Facilities Safety Board
|
 |
| 10:45 a.m. |
Guest Speaker
Ken Picha
Acting Deputy Assistant Secretary for Safety and Security Management,
Office of Environmental Management
(filling in for Dae Chung, Principal Deputy Assistant Secretary)
|
 |
| 11:30 a.m. |
Lunch |
| 1:00 p.m. |
Nuclear Industry Safety Experience
George Mortensen, Institute of Nuclear Power Operations
|
|
| 1:45 p.m. |
NNSA's Approach to Transformational Governance and Oversight
Jim McConnell, Assistant Deputy Administrator for Nuclear Safety,
Nuclear Operations, and Governance Reform, National Nuclear Security Administration |
 |
| 2:30 p.m. |
DOE O 420.1 Natural Phenomena Hazard Requirements
Todd Lapointe, Office of the Chief of Nuclear Safety |
 |
| 2:45 p.m. |
Break |
| 3:15 p.m. |
Panel Discussion: Federal Ownership and Contractor Assurance
Jim McConnell, National Nuclear Security Administration
Ken Picha, Office of Environmental Management
Carol Sohn, Office of Science
Rick Denning, Idaho Operations Office
|
|
| 4:00 p.m. |
Site Lead Program and HSS Oversight
John Boulden, Acting Director, Office of Independent Oversight
Office of Health, Safety and Security |
 |
| 4:30 p.m. |
Occurrence Reporting and Corporate Operating Experience Programs
Jeannie Boyle, Occurrence Reporting Program Manager,
Office of Corporate Safety Programs,
Office of Health, Safety and Security |
 |
Thursday, May 5, 2011 Facility Representatives Track |
| 8:00 a.m. |
Facility Representatives in the Accident Investigation Process
Chuck Lewis, Director, Office of Corporate Safety Programs,
Office of Health, Safety and Security |
 |
| 9:00 a.m. |
Review of Science Sites Hazard Categorization
Carol Sohn, Office of Science |
 |
| 9:30 a.m. |
Break |
| 10:00 a.m. |
Sharing of Good Practices and Lessons Learned For Federal Staff |
- Dan Carter, Los Alamos Site Office: 13.2KV Near Miss Event at TA-55
|
 |
- Garth Reed, Waste Treatment Plant, Hanford: Boiling Liquid Expanding Vapor Explosions
|
 |
- Brian Stickney, Tank Farm Operations, Hanford: C-107 Dome Cut and Mobile Arm Retrieval System
|
 |
- Richard Mayer II, Portsmouth/Paducah Project Office: Lessons Learned for Nondestructive Assay to Support D&D
|
 |
| 11:30 a.m. |
Lunch |
| 1:00 p.m. |
Sharing of Good Practices and Lessons Learned for Federal Staff |
- Dave George, Los Alamos Site Office: Red Fuming Nitric Acid Incident
|
 |
- James Mumma, Nevada Site Office: Area 5 RWMC Watermaster Rollover Event
|
 |
- Patrick Sullivan, Brookhaven Site Office: Terminal Room Relay Fire
|
*Honorable Mention
 |
| 2:00 p.m. |
Operations Assessment Field Handbook Development Session
Mike Childers, Pantex Site Office, and Glenn Gamlin, Carlsbad Field Office, facilitators |
 |
| 2:45 p.m. |
Break |
| 3:00 p.m. |
Sharing of Good Practices and Lessons Learned for Federal Staff |
- David Sanders, Savannah River Site: F-TRU Waste Remediation Facility Puncture Wound
|
*Best FR Lessons Learned Presentation
 |
- Brian Jones, Pantex Site Office: Dropped HE Billet
|
 |
- Robert (Ed) English, Savannah River Site: K-area Cooling Tower Demolition
|
*Honorable Mention
 |
- Gary Schmidtke, Sandia Site Office: Sandia Severe Weather Lessons Learned
|
 |
- Richard Mayer II, Portsmouth/Paducah Project Office: Lessons on the Depleted UF6 Conversion Project
|
 |
| 4:45 p.m. |
Summary/Closing Remarks
Earl Hughes, Facility Representative and Safety System Oversight Program Manager
Office of Nuclear Facility Safety Programs
Office of Health, Safety and Security |
|
| 5:00 p.m. |
Adjourn |
Thursday, May 5, 2011 Safety System Oversight Track |
| 8:00 a.m. |
Welcome |
|
| 8:05 a.m. |
Safety System Oversight Development Session:
Contractor System Engineering Program Assessment Guidelines
Carl Sykes, Chief of Defense Nuclear Safety Staff, Facilitator |
 |
| 9:30 a.m. |
Break |
| 10:00 a.m. |
- Joel Fox, Waste Treatment Plant, Hanford: Radial HEPA Filter Testing
|
 |
- Elaine Diaz, Waste Treatment Plant, Hanford: Safety System Oversight in New Construction
|
|
| 11:30 a.m. |
Lunch |
| 1:00 p.m. |
- Michael Harmon, Savannah River Nuclear Solutions: Power Distribution Harmonics
|
 |
- Pranab Guha, HSS: Safety Instrumented System (SIS) Technical Standard
|
 |
- Jeff Williams, Los Alamos Site Office: Case Study: SIS Technical Standard Application
|
 |
| 2:45 p.m. |
Break |
| 3:00 p.m. |
- Mike Frehner, National Security Technologies: Nevada Site Configuration Management Program
|
 |
- Brian Rhodes, Pantex Site Office: Safety Class Fire Water Supply Project
|
 |
| 5:00 p.m. |
Adjourn |
| 9:50 a.m. to 12:15 p.m |
Atomic Testing Museum |
|