Nuclear Facility Design
Draft 2/6/2006
Suggested lines of inquiry and
review approach
Performance
Objective 1: Contractor Program Documentation
The Contractor Integrated Safety Management (ISM) System
Description includes mechanisms for integrating ISM into the
project design activities (DOE O 413.3, CRD, #12 and DEAR 970
-5404-2)
- Is an ISMS description developed that integrates the 5
core functions and 7 guiding principles into project
activities and personnel roles and responsibilities?
- Is there evidence through project activities that design
decisions and changes are based on or influenced by efforts
to eliminate hazards, minimize hazards, mitigate
consequences, and preclude accident events that could
release hazardous materials?
- Does the Project Execution Plan include a description of
ISM implementation for all phases of the project?
- Do project specific performance measures include
explicit links to the site/or project ISM system
description?
- Do contractor implementing mechanisms and procedures
identified in the PEP provide for close coordination between
the development of the facility design and the safety
analysis documents? (e.g. HAD, FHA, and emergency response
evaluations)
- Do contractor implementing mechanisms include procedures
for defining the project/design requirements, identifying
hazards, performing design, analyzing the hazards and
ensuring appropriate controls are built into the design, and
obtaining approval of the design by the NNSA Site Office and
the NNSA acquisition executive?
- Are contractor implementing mechanisms in place to
ensure that ISM requirements are communicated and
incorporated into subcontractor or other support
organization design/project activities?
- Are feedback and improvement mechanisms in place to
identify, evaluate, and correct design/project safety
issues?
- Do the project ISM implementing mechanisms provide for a
systematic review and approval of all applicable standards
for the each of the various stages of design?Are Facility
and safety SSC design requirements are traceable to
applicable Federal, DOE, State, Site and Local laws and
regulations?
Performance
Objective 2: Contractor Program Implementation
- Is there a listing of all potentially applicable codes
and standards identified in DOE O 420.1A and whether they
are applicable and need to be incorporated into the Design
efforts for each of the various phases of design?
- Is there an integrated project team that coordinates the
development of the following documents during each of the
associated project phases?
- Conceptual Design
- Define Scope of work
- Mission Functional and Performance Requirements
Established
- Analyze Hazards
- Hazard Categorization (HAD)
- Preliminary Hazards Analysis (PHA)
- Preliminary FHA
- Preliminary Accident Analyses
- Develop/Implement Controls (Develop Design
Requirements)
- Develop Safety Function Definitions
- Preliminary Identification of Safety SSCs and
Administrative Controls
- Design Requirements Established
- Identify Design Codes and Standards
- Perform Work/Design
- FDD Established
- SDDs Established
- PSAR Development Initiated
- Design Packages
- Conceptual Design Report
- Feedback and Improvement (review and validation)
- PSAR Development Initiated
- DOE Review/Approval of CDR
- DOE Review/Approval of HAD
- Critical Decision-1
- Preliminary Design
- Define Scope of work
- FDD under Change Control
- SDDs under Change Control
- CDR establishes Baseline
- Analyze Hazards
- Detailed Process Hazards Analysis Drafted
- Design Basis Accidents Identified
- Some Preliminary Analysis Completed
- Develop/Implement Controls (Develop Design
Requirements)
- Safety SSC Functional Requirements Established
- SSC Performance Requirements Established
- Design Requirements Updated
- Codes and Standards Updated
- Perform Work/Design
- FDD updated
- SDDs updated
- Preliminary Design Package
- Feedback and Improvement (review and validation)
- PSAR Drafted
- DOE Review/Accept Preliminary Design
- Review PSAR Draft
- Critical Decision-2
- Final (Detailed) Design
- Define Scope of work
- SSC Design Requirements under Change Control
- FDD and SDD under Change Control
- Preliminary Establishes a Baseline
- Analyze Hazards
- Detailed Process Hazards Analysis Drafted
- Accident Analysis Completed & DBAs Fully
Established
- Safety SSC Functional Requirements Finalized
- SSC Performance Requirements Fully Designed
- Develop/Implement Controls (Develop Design
Requirements)
- Design Requirements Finalized
- Codes and Standards Finalized
- Procurement Specifications are Prepared
- Perform Work/Design
- FDD Updated
- SDDs Updated
- Preliminary Design and Procurement Package
- Feedback and Improvement (review and validation)
- PSAR Completed
- DOE Review/Accept Final Design Package
- DOE Review/Approval of PSAR (SER)
- Critical Decision-3
- Are design control procedures and mechanisms are
explicitly identified and documented?
- Do design reports demonstrate that requirements and
design work and design changes are met?
- Are design control procedures and mechanisms reviewed
and approved?
- Is surveillance of design control work completed
performed to ensure that procedures and mechanisms are being
properly executed?
- Does a design configuration management plan exist that
defines the records that need to be developed and
maintained?
- Are evaluations of design record periodically conducted?
- Are design calculations and analyses documented and
retrievable?
- Are design documents prepared, reviewed, approved, used,
and revised in accordance with prescribed processes?
- Does a formal process exist to approve deviations from
design requirements?
- Are Integrated Safety Management principles used during
design defined and documented?
- Are Documented Safety Analysis requirements planned and
scheduled and include appropriate design inputs and outputs?
- Are design interfaces identified, evaluated, and
incorporated. Interfaces include national laboratories,
design agencies, Architect Engineering firms,etc?
- Do design calculations and analyses demonstrate that
requirements and design bases are met?
- Are contractor mechanisms for completing design reviews
explicitly used?
- Are contractor design reviews completed by appropriate
personnel who are properly trained?
- Are independent peer reviews completed in accordance
with a documented process?
- Are SSC designs validated prior to field implementation
in accordance with a defined process?
- Are SSC design criteria linked to the safety function
and functional requirements identified in the safety basis
documents?
- Do SSC drawings include applicable design requirements
derived from safety functions and functional requirements
identified in the authorization basis?
- Is SSC design criteria explicitly checked against the
set of appropriate standards?
- Is failure analysis, including consideration for single
point failures is included in the SSC design process?
- Are specific training and qualification programs for
design personnel established?
- Are individual training records for design personnel
maintained?
- Do design personnel receive continuing training based on
an established process?
Performance
Objective 3: DOE Line Management Oversight
- Are Site Office Project personnel qualified and trained
to the Project Management System with respect to ES&H/QA
requirements integration?
- Do Site Office Project personnel develop plans and
schedules, assign resources and assess progress on a
day-to-day basis, ensuring safety is integrated into both
Federal and Contractor management and work practices at all
levels? (DOE 413.3)(Draft Project Management Practices
(10/00), Figure 3-9)
- Is there a process to incorporate ES&H/QA lessons
learned information into planning and/or training programs
(FRAM 9.6.1.1, 9.6.2.1)
< BACK TO PREVIOUS PAGE