Nuclear Facility Design
Draft 2/6/2006
FUNCTIONAL AREA GOAL: Headquarters and Field organizations
and their contractors ensure that nuclear facilities are
designed to assure adequate protection for the public,
workers, and the environment from nuclear hazards.
REQUIREMENTS:
- 10 CFR 830.120
- 10 CFR 830 subpart B
- DOE O 413.3
- DOE O 420.1B
- DOE O 414.1C
- DOE O 226.1
- DOE M 426.1
- DEAR 970-5404-2
GUIDANCE:
- DOE G 420.1-1
- Project Management Practices, Integrated Quality ( Rev
E, June 2003)
- DOE Implementation Plan for DNSB Recommendation 2004-2
Performance Objective 1: Contractor Program
Documentation
Contracts between and the contractors who operate nuclear
facilities contain adequate requirements concerning the
conduct of nuclear facility safety design for nuclear facility
capital projects and major modifications and the contractors
have developed comprehensive processes/procedures for
performing these requirements.
Criteria:
- Contractor processes and procedures define roles and
responsibilities for engineering duties and tasks such as
design changes, standards identification, testing, and
formal design reviews for nuclear facility capital projects
and major modifications (DOE FRAM, DOE O 414.1C).
- Contractor processes and procedures ensure that detailed
application of nuclear facility structure, systems, and
components (SSC) design requirements are guided by the
safety analysis that identify and establish safety SSC
functional requirements and meet applicable DOE and industry
nuclear facility design requirements (DOE P 450.5, DOE O
420.1B section 4.1.1.1).
- Contractor processes and procedures ensure that nuclear
facility SSCs are designed to withstand the effects of
natural phenomena hazards (NPH) as necessary to ensure the
confinement of hazardous material based on the results of
the preliminary documented safety analysis (PDSA) (DOE P
450.5, DOE O420.1B section 4.4.2).
- The Contractor Integrated Safety Management (ISM) System
Description includes mechanisms for integrating ISM into the
project design activities (DOE O 413.3, CRD, #12 and DEAR
970 -5404-2)
- Contractor processes and procedures incorporate
applicable quality assurance requirements for the conduct of
engineering design functions (DOE O 413.3 CRD #11, QA
criterion 6 -Design)
Suggested
Lines of Inquiry and Review Approach
Performance Objective 2: Contractor Program
Implementation
contractors responsible for operation of nuclear facilities
have effectively implemented processes/procedures to ensure
nuclear facility capital projects and major modifications are
designed in accordance with contract requirements in order to
provide adequate protection for the public, workers, and the
environment from nuclear hazards.
Criteria:
- The following nuclear safety design criteria have been
explicitly addressed during the various phases of the
nuclear facility design process (DOE O 420.1 section 4.1):
- Radioactive and Hazardous Material Inventory
- Conservative Facility Design
- Defense in Depth concepts and principles have been
considered in the design, such as including minimization
of material, conservative design margins, quality
assurance, and multiple barriers to release
- Confinement ventilation has been incorporated into
the design with preference on use of active confinement
(DNFSB 2004-2)
- Preventative Features
- Mitigating Features
- Siting Criteria
- Facility Siting criteria have been evaluated to
determine minimize potential impact to public and
adjacent facilities
- Site planning considered the consequences of all NPH
type events
- NPH
- - Design process considers potential damage and
failure of SSCs from both direct and indirect NPH,
including damage from failure of other SSCs
- Seismic requirements of executive order 12699 have
been identified in the design
- Access Control
- Facility design ensures occupational exposure is
maintained within limits of 10CFR 835 and includes
provisions for maintaining exposure ALARA and to
facilitate decontamination during operation
- Accessibility and Maintainability
- Reliability, Availability, and Maintainability
objectives have been identified for designated SSCs
- Human Factors Engineering
- Design to Facilitate Deactivation, Decontamination,
and Decommissioning
- Design processes/procedures ensure that SSC functional
requirements are identified early in the design process.
- Applicable SSC functional design criteria such as
single failure, equipment qualification, etc, from section
4 of DOE G 420.1A have been incorporated into the system
level functional design.
- Contractor processes and procedures for implementing ISM
through each of the project design phases have been
effectively implemented. (DOE O 413.3, CRD, #12 and DEAR 970
-5404-2)
- The engineering and safety analysis processes are
integrated to ensure that the design includes a complete
set of SSCs required to protect the workers and the public
from potential uncontrolled releases
- Contractor implementing design processes procedures
establish the expectations for the required safety,
environment, quality, engineering documentation at the
various stages of the design process and provide for
integration of these various technical disciplines and
documents
- The contractor implementing processes/procedures
ensure that appropriate standards are identified and
evaluated for the design of safety SSCs based on the
relative importance to safety as determined by the hazard
analysis and required consensus codes. (ISMS Guiding
Principle #XX)
- Contractor design processes/procedures ensure that
ES&H requirements, as delineated in Federal, DOE,
State, Site and Local laws and regulations are explicitly
included in the design process
- Quality assurance requirements are implemented during
the conduct of engineering design functions and activities
(DOE O 413.3 CRD #11, QA criterion 6 -Design)
- Facility processes and procedures ensure that inputs
to design engineering activities are clearly identified
and approved by appropriate facility management prior to
the start of design activities and that changes to those
inputs are controlled with appropriate rigor (10CFR830
Subpart A, Criterion 6, 48CFR970.5203(a), DOE O 414.1C
4(b)(6))
- Facility processes and procedures ensure that
management oversight of the design process is adequate to
ensure that design deliverables fulfill requirements,
including physical installation of the design (10CFR830
Subpart A, Criterion 6, DOE O 414.1C 4(b)(6), DOE O 433.1
4(a))
- Facility processes and procedures clearly define
expected design deliverables sufficient to maintain
configuration management, and to maintain and verify
compliance with facility requirements (10CFR830 Subpart A,
Criterion 6, DOE O 420.1A 4.5.1.2, DOE O 433.1 4(a))
- Facility processes and procedures ensure that
post-design changes are tracked and analyzed to identify
problems with the design process, with appropriate
corrective actions assigned and tracked to closure
(48CFR970.5203 (b), DOE O 414.1C, 4(b)(3))
- Facility processes and procedures provide for the
identification and control of design interfaces (NQA-1,
Requirement 3, Design Control, section 700 Interface
Control)
- Facility processes and procedures describe
requirements for performing design analysis (NQA-1,
Requirement 3, Design Control, section 400 Design
Analysis)
- Facility processes and procedures describe
requirements for performing design verification, including
conduct of design reviews (NQA-1, Requirement 3, Design
Control, section 500 Design Verification)
- Facility processes and procedures ensure that
compliance with the facility's safety basis is adequately
considered throughout the design process, from inception
through acceptance (10CFR830, Subpart A, Criterion 5, DOE
O 420.1A 4.5.1.2, DOE O 433.1 4(a))
- Facility processes and procedures ensure that design
output contains proper Quality Assurance classifications
for any needed components, total system classification,
and resultant drawing changes (10CFR830 Subpart A,
Criterion 7, 48CFR970.5203(b), DOE O 414.1C 4(b)(7))
- Contractor processes and processes include appropriate
software quality assurance requirements for design
analysis software tools (DOE O 414.1C section XXX)
- Contractor processes and procedures require the
designation of a Design Authority responsible for the
final approval of design requirements (DOE STD 1073
section XXX)
- The technical baseline for identified safety SSCs has
been established and is being controlled per the contractors
Configuration management program (DOE O 413.3 CRD
#9)
- Contractor personnel have been assigned system
engineering duties and responsibilities for identifying and
integrating nuclear safety requirements and establishing and
maintaining the technical baseline for nuclear facility SSCs
(DOE O 420.1B section XXX)
- Contractor personnel are trained and qualified to
perform their assigned duties and responsibilities relative
to nuclear facility design and peer review activities (ISM
Guiding Principle XX)
Suggested
Lines of Inquiry and Review Approach
Performance Objective 3: DOE Line Management
Oversight:
Defined requirements through appropriate contract
mechanisms are in place to ensure that nuclear facilities are
designed to assure adequate protection for the public,
workers, and the environment. HQ and/or Field/Site Offices
have assigned personnel and developed processes/procedures for
the activities they must conduct in support of contractor
nuclear facility safety design activities. HQ and/or
Field/Site Offices have assigned personnel and established and
implemented effective oversight processes to ensure that the
contractor nuclear facility design activities are properly
conducted.
Criteria:
- Field or Site Office has determined the appropriate
level of resources and formal expectations for conducting
effective oversight of contractor nuclear facility design
activities (FRAM, DOE O 226.1)
- Field or Site Office has assigned technically competent,
trained and qualified personnel to perform activities in
support of and effective oversight of contractor facility
nuclear safety design activities (FRAM; DOE M
426.1).
- Field or Site Office nuclear facility design/oversight
procedures and processes require federal staff involvement
in standards identification, hazards analysis, design
review, and review of controls (FRAM 9.3.1, 9.4.1, 9.4.2,
Draft Program and Project Management Manual/Draft Project
Management Practices (10/00).
- Site Office nuclear facility design oversight procedures
and processes include documented feedback and improvement
mechanisms through self-assessment, monitoring against
performance objectives, occurrence reporting,
critiques/management reviews, external reports, routine
observation, and activity level feedback. (FRAM 9.6.1, DOE O
226.1)
- Site Office oversight activities of nuclear facility
design activities are being effectively conducted as
evidenced by the following:
- Completion of scheduled formal assessments,
operational surveillances, and other oversight activities.
- Evaluation and communication of assessment results
including expected actions for resolution of identified
issues.
- Development, tracking, and closure of corrective
actions.
- Evaluation of effectiveness of specific corrective
actions.
- Evaluation of effectiveness of the overall nuclear
facility design activities.
- oversight includes an evaluation that the contractor's
implementation of the nuclear facility design activities
demonstrates effective integration and application of
appropriate functions and principles of the Site Integrated
Safety Management System
Suggested
Lines of Inquiry and Review Approach
< BACK TO PREVIOUS PAGE