Nuclear Facility Design

Draft 2/6/2006

FUNCTIONAL AREA GOAL: Headquarters and Field organizations and their contractors ensure that nuclear facilities are designed to assure adequate protection for the public, workers, and the environment from nuclear hazards.

REQUIREMENTS:

GUIDANCE:

Performance Objective 1: Contractor Program Documentation

Contracts between and the contractors who operate nuclear facilities contain adequate requirements concerning the conduct of nuclear facility safety design for nuclear facility capital projects and major modifications and the contractors have developed comprehensive processes/procedures for performing these requirements.

Criteria:

  1. Contractor processes and procedures define roles and responsibilities for engineering duties and tasks such as design changes, standards identification, testing, and formal design reviews for nuclear facility capital projects and major modifications (DOE FRAM, DOE O 414.1C).
     
  2. Contractor processes and procedures ensure that detailed application of nuclear facility structure, systems, and components (SSC) design requirements are guided by the safety analysis that identify and establish safety SSC functional requirements and meet applicable DOE and industry nuclear facility design requirements (DOE P 450.5, DOE O 420.1B section 4.1.1.1).
     
  3. Contractor processes and procedures ensure that nuclear facility SSCs are designed to withstand the effects of natural phenomena hazards (NPH) as necessary to ensure the confinement of hazardous material based on the results of the preliminary documented safety analysis (PDSA) (DOE P 450.5, DOE O420.1B section 4.4.2).
     
  4. The Contractor Integrated Safety Management (ISM) System Description includes mechanisms for integrating ISM into the project design activities (DOE O 413.3, CRD, #12 and DEAR 970 -5404-2)
     
  5. Contractor processes and procedures incorporate applicable quality assurance requirements for the conduct of engineering design functions (DOE O 413.3 CRD #11, QA criterion 6 -Design)

Suggested Lines of Inquiry and Review Approach

Performance Objective 2: Contractor Program Implementation

contractors responsible for operation of nuclear facilities have effectively implemented processes/procedures to ensure nuclear facility capital projects and major modifications are designed in accordance with contract requirements in order to provide adequate protection for the public, workers, and the environment from nuclear hazards.

Criteria:

  1. The following nuclear safety design criteria have been explicitly addressed during the various phases of the nuclear facility design process (DOE O 420.1 section 4.1):
  2. Contractor processes and procedures for implementing ISM through each of the project design phases have been effectively implemented. (DOE O 413.3, CRD, #12 and DEAR 970 -5404-2)
  3. Quality assurance requirements are implemented during the conduct of engineering design functions and activities (DOE O 413.3 CRD #11, QA criterion 6 -Design)
  4. The technical baseline for identified safety SSCs has been established and is being controlled per the contractors Configuration management program (DOE O 413.3 CRD #9)
     
  5. Contractor personnel have been assigned system engineering duties and responsibilities for identifying and integrating nuclear safety requirements and establishing and maintaining the technical baseline for nuclear facility SSCs (DOE O 420.1B section XXX)
     
  6. Contractor personnel are trained and qualified to perform their assigned duties and responsibilities relative to nuclear facility design and peer review activities (ISM Guiding Principle XX)

Suggested Lines of Inquiry and Review Approach

Performance Objective 3: DOE Line Management Oversight:

Defined requirements through appropriate contract mechanisms are in place to ensure that nuclear facilities are designed to assure adequate protection for the public, workers, and the environment. HQ and/or Field/Site Offices have assigned personnel and developed processes/procedures for the activities they must conduct in support of contractor nuclear facility safety design activities. HQ and/or Field/Site Offices have assigned personnel and established and implemented effective oversight processes to ensure that the contractor nuclear facility design activities are properly conducted.

Criteria:

  1. Field or Site Office has determined the appropriate level of resources and formal expectations for conducting effective oversight of contractor nuclear facility design activities (FRAM, DOE O 226.1)
     
  2. Field or Site Office has assigned technically competent, trained and qualified personnel to perform activities in support of and effective oversight of contractor facility nuclear safety design activities (FRAM; DOE M 426.1).
     
  3. Field or Site Office nuclear facility design/oversight procedures and processes require federal staff involvement in standards identification, hazards analysis, design review, and review of controls (FRAM 9.3.1, 9.4.1, 9.4.2, Draft Program and Project Management Manual/Draft Project Management Practices (10/00).
     
  4. Site Office nuclear facility design oversight procedures and processes include documented feedback and improvement mechanisms through self-assessment, monitoring against performance objectives, occurrence reporting, critiques/management reviews, external reports, routine observation, and activity level feedback. (FRAM 9.6.1, DOE O 226.1)
     
  5. Site Office oversight activities of nuclear facility design activities are being effectively conducted as evidenced by the following:
  6. oversight includes an evaluation that the contractor's implementation of the nuclear facility design activities demonstrates effective integration and application of appropriate functions and principles of the Site Integrated Safety Management System

Suggested Lines of Inquiry and Review Approach



< BACK TO PREVIOUS PAGE