Environmental Compliance
Draft 1/11/2006
FUNCTIONAL AREA GOAL: The site has an Environmental
Management System (integrated into the site's Integrated
Safety Management System) (ISMS/EMS) which ensures compliance
with regulatory requirements through identification of
environmental compliance requirements, incorporation of
requirements into site policies and procedures, periodic
assessment of regulatory compliance, and identification and
implementation of corrective action where needed.
REQUIREMENTS:
Compliance Management Requirements
- DOE O 450.1, Environmental Protection Program
- DOE P 450.2A, Identifying, Implementing, and Complying
with Environment, Safety and Health Requirements
- DOE P 450.4, Safety Management System Policy
- DOE P 450.7, DOE Environment, Safety and Health Goals
- DOE P 411.1, Safety Management Functions,
Responsibilities, and Authorities Policy
- DOE P 226.1, Department of Energy Oversight Policy
- DOE O 226.1, Implementation of DOE Oversight Policy
- DEAR clause 970.5204-2, Laws, Regulations, and DOE
Directives
- DEAR clause 970.5223-1, Integration of Environment,
Safety, and Health into Work Planning and Execution
Underlying Legal Requirements:
- Applicable Federal Laws and Regulations
- Applicable State Laws and Regulations
- Applicable Local Laws and Regulations
Note: these requirements are intentionally not
enumerated; compliance is required with all applicable
requirements.
- Environmental Permit Conditions
- Consent Orders and Compliance Agreements
- Federal Facility Agreements
GUIDANCE:
- DOE G 450.1-2, Implementation Guide for Integrating
Environmental Management systems into Integrated Safety
Management Systems
- DOE G 450.4, Integrated Safety Management System Guide
Performance Objective 1: Contractor Program
Documentation
The contractor's ISMS/EMS includes procedures to identify
all applicable legal requirements. It includes policies and
procedures to ensure compliance with these requirements. The
ISMS/EMS includes a program to assess regulatory compliance,
identify potential non-compliances, and implement corrective
actions.
Objective 1.1: All Applicable Legal Requirements and
Identified: Identify activities with significant
environmental impacts'; 'Identify the hazards
Criteria:
- The ISMS/EMS includes policies and procedures to
identify activities which are subject to regulation. (DOE O
450.1 §4.a.(2)).
- Before work is performed, the associated hazards are
evaluated and an agreed-upon set of ES&H requirements is
established. (DEAR Clause 970.5223 (a)(5))
[Lines of inquiry to be developed]
Objective 1.2: Ensure that Policies and Procedures
are in Place to Assure Compliance: Manage control and
mitigate the impacts of activities with significant
environmental impacts'; 'Develop and implement hazard
controls
- The ISMS/EMS provides for the systematic planning of
programs for compliance with applicable requirements. (DOE O
450.1 §4.a.(1)).
- The ISMS/EMS includes policies and procedures to ensure
compliance with regulatory requirements. (DOE O 450.1
§4.a.(2))
- The ISMS/EMS includes procedures to manage, control, and
mitigate the potential impacts of site activities with
significant environmental impacts. The ISMS/EMS provides for
the integrated execution of programs for compliance with
applicable requirements. (DOE O 450.1 §4.a.(2); .DOE O 450.1
§4.a.(1))
[Lines of inquiry to be developed]
Objective 1.3 Processes are established to assess
compliance and implement corrective actions where
needed: Assess performance and implement corrective
actions where needed'; 'Provide Feedback and Continual
Improvement
Criteria:
- The ISMS/EMS includes policies and procedures to assess
performance of programs for compliance with applicable
requirements. (DOE O 450.1 §4.a.(1)(c); §4.a.(2))
- The ISMS/EMS includes policies and procedures to
implement corrective actions where needed. (DOE O 450.1
§4.a.(2))
- Contractor compliance assessment programs are
established as part of ISM/EMS, within the framework of DOE
P 226.1 and DOE O 226.1. (DOE O 450.1 §5.d.(16))
[Lines of inquiry to be developed]
Performance Objective 2: Contractor Program
Implementation
Work is conducted in compliance with all applicable legal
requirements. The contractor is assured that legal
requirements are being met.
Objective 2.1: Work is Performed in Compliance with all
Applicable Requirements: Manage control and mitigate
the impacts of activities with significant environmental
impacts'; 'Perform Work within Controls
Criteria:
- Before work is performed, the associated hazards are
evaluated and an agreed-upon set of ES&H requirements is
established. (DEAR Clause 970.5223 (b)(5))
- The ISMS/EMS includes training
- to identify activities which are subject to
environmental regulation
- to manage, control, and mitigate the potential impacts
of these activities, and
- to assess compliance performance and implement
corrective actions where needed. (DOE O 450.1
§4.a.(2)
- The contractor complies with, and assists the DOE in
complying with, ES&H requirements of all applicable laws
and regulations. (DEAR Clause 970.5223)
[Lines of inquiry to be developed]
Objective 2.2 The contractor assesses compliance with
legal requirements, and implements corrective actions where
needed.
Criteria:
- Contractor submits, for DOE annual review and approval,
detailed contractor assurance system program descriptions to
address aspects of operations including environment, safety,
and health among others. (DOE O 226.1)
- Compliance is assessed as a component of the
implementation of DOE P 226.1 and DOE O 226.1. Contractor
compliance assessment programs are established within the
framework of DOE P 226.1 and DOE O 226.1, and continue to be
effective. (DOE O 450.1 §5.b.; DOE O 450.1
§5.d.(16))
- ISMS/EMS environmental goals, objectives and targets are
reviewed and updated annually. (DOE O 450.1 4.a.(3)
[Lines of inquiry to be developed]
Performance Objective 3: DOE Line Management
Oversight
DOE line management assures that all operations under their
purview are operating in compliance with applicable legal
requirements. DOE is in compliance with legal requirements
applicable to DOE.
Criteria:
- DOE ensures compliance with legal requirements. (DOE P
411.1)
- DOE assesses ISMS/EMS implementation, including
regulatory compliance, as a component of the implementation
of DOE P 226.1 and DOE O 226.1. (DOE O 450.1 §5.b.)
- Contractor compliance performance is reviewed as part of
the performance objectives, performance measures, and
commitments through the annual ISM review process
established pursuant to DEAR 970.5223-1 (e). (DOE O 450.1
§5.d.(17))
[Lines of inquiry to be developed]